On August 3, the Lushan Photovoltaic Power Generation Project was officially started.
The project is located in Xiaowan Town, Fengqing County, Lincang City, Yunnan Province, with a total investment of 385 million yuan, an AC side installed capacity of 90 MW and a DC side installed capacity of 107.6 MW. The intelligent construction mode of "block power generation and centralized grid connection" is adopted. The owner of the
project is Huaneng Lancangjiang New Energy Co., Ltd. Previously, in March 2026, the owner of the project had publicly tendered for the general contracting of civil engineering and installation. In May 2026, Sinohydro Bureau 7 Co., Ltd. won the bid for the construction and installation of the project with about 78.8722 million yuan.