On August 3, the bidding for the 300 MW/1200 MWh independent energy storage project in Weining County, Bijie City was terminated. Tenderee: Penghe (Weining) Energy Technology Co., Ltd.
The announcement shows that the reason for the rejection of the bid is that the price of the equipment involved in the project has fluctuated considerably in the near future, and the tenderer has decided to terminate all the current bidding process and reorganize the bidding after the relevant conditions have been adjusted and improved.
It is understood that the project uses liquid-cooled lithium iron phosphate technology route, a total of 120 energy storage units with a capacity of 5 MW/10 MWh, and a new 220 kV booster station. The tender was launched on June 4, and the bid opening and evaluation were completed on June 25. The consortium led by the Sixth Design and Research Institute of Machinery Industry Co., Ltd. offered about 1.11 billion yuan and became the first successful candidate.
浙公网安备33010802003254号