Recently, the Henan Development and Reform Commission issued a notice (Notice on the Inspection of the Construction of Independent Energy Storage Power Stations) that independent energy storage projects that have not yet been put into operation for 6-15 months will be subject to a comprehensive insp ection, involving 44 projects. Total size 6.11 GW/16.11 GWh. The main purpose of this inspection
in Henan is to strictly prohibit the "circle without building" behavior, and the follow-up inspection will be carried out to clear the projects that have not been substantially started, and the corresponding power access review opinions will be abolished. In March
this year, Henan Province issued a document ( "Several Measures to Promote the High-quality Development of New Energy Storage in Henan Province "), which made it clear that the energy storage project should start within 6 months after obtaining the approval of the access system and be completed and put into operation within 15 months.