On December 3, the photovoltaic power generation project of the 222nd Regiment of the 12th Division of Southwest Oil and Gas Field Sinkiang Production and Construction Corps (Phase I 240000 kilowatts)-public bidding for the implementation of part of EPC general contracting (photovoltaic field tender section) in 2025. The tenderer
is Xinjiang Beiting Southwest Oil New Energy Co., Ltd. The project is located in Fukang City, Changji Prefecture, Xinjiang. It is planned to build a 120 MW photovoltaic power station on the AC side (147.0144 MWp on the DC side). The bidding scope covers the whole process of design, procurement, construction, acceptance, handover and warranty. The performance requires the bidder to have at least one photovoltaic EPC performance of 100MW or above from 2022. The construction period of the project is 90 days (including a 30-day design period). Consortium bidding is accepted. The bidding and bid opening time is 08:00 on December 24, 2025.