On August 13, China Coal Group issued two tender announcements for photovoltaic EPC general contracting.
China Coal Pingshuo Group's 600MW Off-grid Renewable Energy Hydrogen Production Phase I Project (Photovoltaic Part)
is located in the coal mining subsidence treatment and backfilling reclamation area of Pingshuo Mining Area, Pinglu District, Shuozhou City, Shanxi Province, with a DC installed capacity of 111.45 MW and a construction period from November 1, 2025 to March 31, 2027.
The bidder must have one 100MW and above photovoltaic EPC general contracting performance, and one 100MW and above photovoltaic construction drawing design performance and main construction general contracting performance respectively, and the consortium is allowed to bid.
Bid closing/opening time: 15:30, September 3, 2025.
China Coal Xinji Energy Jiangxi Jinxi County Xiqiao 50MW Photovoltaic Power Generation Project
The project is located in Langya Town, Jinxi County, Fuzhou, Jiangxi, with a DC installed capacity of 50 MWp and 79,365 630 Wp double-sided double-glass modules. Block power generation and centralized grid connection.
The bidder must have the operation performance of at least one "50 MW and above photovoltaic EPC (including booster station) and 110kV and above transmission project" since January 1, 2022, and the consortium bidding is not accepted.
Bid closing/opening time: 10:00, September 2, 2025.