On August 18, the second batch of photovoltaic project components of China Resources Power in 2025 were collected and opened, which was divided into three bidding sections. Purchase N-type TOPcon double-sided double-glass PV module 3GW.
Bid section 1 (1500MW): 22 enterprises bid, with the quotation of 0.677 ~ 0.776 yuan/W and the average price of 0.729 yuan/W;
bid section 2 (1200MW): 22 enterprises bid, with the quotation of 0.690 ~ 0.752 yuan/W and the average price of 0.729 yuan/W;
Bid Section III (300MW): 19 enterprises bid, with the quotation of 0.673 ~ 0.744 yuan/W and the average price of 0.718 yuan/W.
It is reported that the batch of tenders was launched on July 1, postponed on July 15, and finally opened on August 18.