On June 29, the mobilization ceremony of Longji Yongning 400 MW photovoltaic power generation project of Huaneng Ningxia Company was successfully held. The total investment of the

project is about 1.1 billion yuan . According to the tender announcement for general contracting of PC construction of the 400 MW photovoltaic power generation project issued by Huaneng Group on April 11, the project is located in Minning Town, Yongning County, Yinchuan City, Ningxia Hui Autonomous Region, with an installed capacity of 400 MW on the AC side of the photovoltaic field . The installed capacity on the DC side is about 480.2473 MWp . It is originally planned to start construction on May 25, 2026, complete the construction on November 30, 2026, and complete the completion acceptance before May 30, 2028. The total construction period is 190 calendar days.