on June 28, Laidebao Solar Energy Technology (Delingha) Co., Ltd. It was held in the West Export Photovoltaic (Thermal) Industrial Park of Delingha City, Haixi Mongolian and Xizangan Autonomous Prefecture, Qinghai Province. The total investment of

the 500MW photovoltaic project is 1.482 billion yuan , and the annual average power generation will reach 875 million degrees after the project is completed and put into operation. The project is jointly built by CECEP Solar Energy Technology Co., Ltd. and Qinghai Laidebao New Materials Co., Ltd .
Previously, on June 23, the public tender announcement for EPC general contracting of the 500 MW photovoltaic project was issued, and the tenderer was CECEP solar energy. The tender announcement shows that the project is scheduled to complete the full capacity grid connection by December 30, 2026, with a total construction period of 510 days. (For details, please click: EPC Bidding for CECEP Qinghai 500MW Photovoltaic Project! )