On August 17, the official website of Hebei Natural Resources Department announced the approval results, and the construction land of Hebei Huadian Langfang Anci Donggu Port 150 MW photovoltaic project was approved.
Publicity information shows that the Department of Natural Resources of Hebei Province has agreed to transfer and expropriate 0.9952 hectares of collective agricultural land (no arable land) for the construction of 150 MW photovoltaic project in Langfang Anci Donggu Port, Hebei Huadian.

Previous EIA information shows that the project is located in Donggugang Town, Anci District, Langfang City, and the construction unit is Huadian (Langfang Anci District) Science and Technology Development Co., Ltd. The total investment of
the project is 520 million yuan, and it is planned to build a 150 MW photovoltaic power generation project and a new 220 kV booster station (including comprehensive building, ancillary room, electrical prefabricated cabin, GIS, main transformer and structure, etc.). Equipped with 18 MW/36 MWh energy storage system . The scheme of block power generation and centralized grid connection is adopted. The construction period is 12 months.
浙公网安备33010802003254号