The Digital New Energy DataBM. Com was informed that on April 20, The People's Government of Taishun County issued an announcement on the acceptance of the Environmental Impact Assessment Report Form for 150MW Agricultural (Tea) Photo voltaic Power Generation Project in Shiyang Town, Taishun County.

According to the announcement, the project is newly built (relocated), located in Shiyang Town, Taishun County, Wenzhou City, Zhejiang Province, with a total investment of 65545 62000 yuan .
This project is constructed by Taishun Longyuan Hangtai New Energy Co., Ltd. Equity penetration shows that the company is co-funded by Zhejiang Longyuan New Energy Development Co., Ltd. (65%) and Zhejiang Zhengtai New Energy Development Co., Ltd. (35%).

It is worth noting that the project is a major change re-approval project .
The environmental impact assessment documents show that due to the change of land transfer of the project, the location of the enterprise booster station is changed from Ruichang Village to Wangwang Village and Guizhao Village, the location of the booster station is displaced 4095 m to the northwest, the total land area is changed from 0.7027 ha to 0.638 ha, and the main transformer capacity is changed from 150 MW to 158 MW; Due to the change of the location of the booster station, the path of the power collection line is changed, and the total length of the line is reduced by 9.11 km. The total construction period of the
project is 12 months, which is planned to start in June 2026 and be completed in June 2027.