Project Name: Qiqihar Keshan County Xinhua Phase II 100MW Wind Power Project EPC Project Successful Candidate Announcement
Project Overview: Qiqihar Keshan County Xinhua Phase II 100MW Wind Power Project is a 100MW grid-connected wind power project located in Xinhua District, Keshan County, Qiqihar City, Heilongjiang Province. It belongs to the second phase of the county's wind power development project. The project will build a wind farm and related supporting facilities, and the EPC general contracting scope includes the civil engineering, electromechanical and installation construction of the project.
Bid winning information:
First place: Power Construction Corporation of China Jiangxi Electric Power Construction Co., Ltd.
Member of the consortium: Power Construction Corporation of China East China Investigation, Design and Research Institute Co., Ltd.
Bid amount: 67999: RMB 0.99 million
Second place: China Gezhouba Group Electric Power Co., Ltd.
Bidding amount: 69285:9600 yuan
Third place: Henan Engineering Co., Ltd.
of China Power Construction Group Bidding amount: 70089:6300 yuan
Project name: Huaneng Lancang River New Energy Company Street, Banqiao, Shale and other eight photovoltaic projects
in Yunnan Province, including Longjie, Banqiao, Shale and other eight photovoltaic power generation projects, have entered the construction preparation stage, and will start on-site construction in December 2025. It is planned to put all the installed capacity into commercial operation before March 31, 2026, and the specific commencement time shall be subject to the written notice of the Employer or the Supervisor.
Bid winning information:
Bid winning company: Power Construction Corporation East China Investigation, Design and Research Institute Co., Ltd.
Fujian Hidili Construction Engineering Co., Ltd.
Bid winning amount: 61143: 0.67 million yuan
Project name: Chaohusheng Overview of Phase I Construction
Project of Ecological Dredging and Wetland Restoration Project: This project is located in the west half of Chaohu Lake and the estuary of Hangbu River, of which the lakeside wetland is located in the lakeside area between Paihe River and Jiangkou River. The main construction contents include: (1) sediment dredging project, with a dredging area of about 14.16 square kilometers. The work amount of ecological dredging is about 4.06 million cubic meters; (2) sediment consolidation project, a sediment treatment center will be built, with an annual treatment capacity of 1.05 million cubic meters; (3) tail water purification treatment project, with a daily treatment capacity of 50,000 cubic meters, is expected to produce 24.18 million cubic meters of tail water; (4) Lakeside wetland restoration project, including wetland protection project and wetland restoration project, to construct lakeside wetland and restore 2.73 square kilometers of wetland. Estimated
contract price: 0.15 million yuan
37883 Planned construction period: 1066 calendar days
Bidding scope: The main construction contents of this project include dredging of the sediment (using the environmental protection cutter suction process); consolidation of the sediment (geotube bag treatment process); Construction of a sediment treatment center; tail water purification treatment; lakeside wetland restoration, construction of lakeside wetland, restoration of wetland, etc.
Bid winning information:
Bid winner: Power China Port and Channel Construction Co., Ltd.
Anhui Construction Engineering Water Resources Development Investment Group Co., Ltd. Consortium
bid price (RMB): 366594360.80
浙公网安备33010802003254号