On December 17, Guoneng Dadu River Company announced the successful candidates for the public bidding for the procurement of some photovoltaic module equipment for Aba Rong'an 1150MW photovoltaic project . Tongwei Co., Ltd. and Jingke Energy Co., Ltd. were shortlisted. The bid-winning unit price ranges from 0.75-0.756 yuan/W.
It is reported that the tenderer of the project is Guoneng Dadu River Basin Hydropower Development Co., Ltd. The project is located in Rong'an Township, Aba County, Aba Prefecture, Sichuan Province. The AC side capacity of the project is 1150MW, the DC side capacity is 1357.1458 MWp, and the comprehensive capacity ratio is 1.18. The PV modules required for the north of Plot 16 # and Plot 20 # of the PV project are purchased
this time, with a total AC side capacity of about 434.61 MW and a DC side capacity of 513.530 94MWp. N-type TopCon double-sided double-glass 640Wp/645 Wp modules are selected for PV modules.
Component supply is scheduled to be completed by September 30, 2026.

In addition, the tender announcement for EPC general contracting project of Aba Rong 'an 1150MW Photovoltaic Project (Phase I) of Guoneng Dadu River Company was issued on November 28, and the tender has not yet been opened. The EPC general contracting project of
the project (Phase I), with an AC side capacity of about 434.61 MW, is divided into two packages. The first package is located in the 20 # plot, with an AC side capacity of 195.525 MW. The photovoltaic modules are supplied by Party A, excluding the booster station; The second bid package is located in the north of 16 # plot, with AC side capacity of about 239.085 MW, photovoltaic modules supplied by Party A, and a new 220 KV booster station. The total construction period of the
first phase of the project is 11 months, the construction period is planned to be from January 1, 2026 to November 30, 2026, and the full-capacity grid-connected power generation is planned to be completed by November 30, 2026.